Posted in Uncategorized on October 25, 2008 | Leave a Comment »
We prepared most of our beams on top of the garage roof. We then craned them into place on top of the steel or wooden posts….
… placing beams….
Here’s Al, surrounded by some of the timberwork:
…these are rafters, waiting to get lifted up onto the beams….
….placing rafters, which will be spread out into position later….
You can [...]
Read Full Post »
Posted in Uncategorized on October 25, 2008 | Leave a Comment »
You can see all the radiant lines for heating…. we will be capturing excess heat from wastewater and vented air and will transfer that heat into the floors…..
… notice how we insulate the edge of the floor slab so that heat isn’t lost to the outside. The floors will be colored in order to capture [...]
Read Full Post »
… you can also see the in-floor heating pipe (in red) awaiting concrete in the rear section of the house.
There will be a few retaining walls in the front of the house….. more photos to come…..
Read Full Post »